ProjectID Project Name Project Type Current Phase Council District Neighborhood Current Budget Start End Scope of Work
DPW381 ADA Access Ramps in CBD City Funded Bid & Award B Central Business District $382,531.70 Early Winter  2014 Late Winter 2014 #N/A
DPW003 Alcee Fortier Blvd Streetscape (Chef Menteur Hwy - Michoud Lagoon) City Funded Construction E Village de Lest $500,000.00 15-Aug-13 A Early Winter 2014 May include sidewalk or other pedestrian walkway improvements,  bikeways, traffic and pedestrian signage or signalization, landscaping,  lighting, or public art.
DPW004 Algiers (Traffic Signal) City Funded Construction C Algiers Point/ McDonough/ Behrman $3,991,109.00 02-Apr-12 A Late Winter 2013 Traffic signal  improvements
DPW343 Alvar St. (Chef Menteur - Higgins) PTP Complete E Desire Area $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW342 Alvar St. (Higgins - Florida) PTP Complete E Desire Dev $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW009 Audubon Blvd. (Willow St - S. Claiborne Ave) City Funded Complete A Audubon $6,177,231.00 18-Oct-10 A 26-Jun-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW363 Banks St. (Carrollton - St. Patrick) PTP Bid & Award A Mid-City $829,492.00 06-Nov-13 A Spring 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW384 Baronne St. (Canal St - Calliope St.) PTP Design C Central Business District $1,392,336.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW354 Basin St. (Canal - N. Claiborne) PTP Bid & Award C Treme - Lafitte $1,878,613.00 22-Nov-13 A 03-Dec-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW010 Bayou Rd Streetscape (Broad St - Rocheblave St) City Funded Bid & Award A Seventh Ward $745,410.00 Early Winter  2014 Spring 2014 May include sidewalk or other pedestrian walkway improvements,  bikeways, traffic and pedestrian signage or signalization, landscaping,  lighting, or public art.
DPW399 Behrman (Marr - Behrman Hwy) PTP Design C Behrman $3,507,400.00 Summer 2014 Early Winter 2015 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW011 Berkley Dr (Huntlee Canal - Woodland Dr) City Funded Complete C Old Aurora $6,646,591.00 14-Feb-11 A 15-Mar-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW012 Berkley Dr (Kabel Dr - Huntlee Dr), Somerset Dr (Berkley Dr - MacArthur Blvd) City Funded Design C Old Aurora $6,346,899.00 Spring 2014 Early Winter 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW364 Bienville St. (Jefferson Davis - Carrollton) PTP Bid & Award AB Mid-City $518,478.00 06-Nov-13 A Spring 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW313 Broad and Washington Streetscape (S. Broad (Fourth - Louisiana) Washington (S. White - Dorgenois) City Funded Bid & Award B Broadmoor $200,000.00 Early Winter  2014 Spring 2014 May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW014 Broad St. and Lafitte St Streetscape (Bienville St - Orleans Ave) City Funded Bid & Award AB Tulane - Gravier $600,000.00 Spring 2014 Summer 2014 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW016 Broadmoor Streetscape (General Pershing from Broad St. to Miro St.) City Funded Complete B Broadmoor $381,439.00 23-Aug-12 A 05-Feb-13 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW361 Broadway St. (Fountainbleau - Leake) PTP Complete AB Audubon $3,074,065.00 17-Apr-13 A 22-Aug-13 A Removal  and replacement of the sidewalk intersections for the installation of the  compliant ADA ramps and the installation of the ADA ramps in the  medians.
DPW367 Burgundy St. (Canal - Esplanade) PTP Complete C French Quarter $1,382,353.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW385 Burgundy St. (Esplanade - Elysian Fields) PTP Design C Marigny & Bywater Neighborhoods $880,000.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW018 Camp (Valmont - Jefferson), Chestnut/Coliseum (Valmont - Leontine), Leontine/Valmont (Mag-Prytania) City Funded Design B Uptown $7,994,974.00 Spring 2016 Summer 2016 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW019 Camp St. (Canal - US 90) City Funded Complete B Central Business District $1,274,264.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of trees, ADA  ramps and bike lane signage & striping.
DPW199 Camp St. (Louisiana Ave - Washington Ave) City Funded Design B Touro $2,453,746.00 Early Winter 2015 Fall 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW020 Canal Blvd. Reconstruction (Robert E. Lee Blvd - Amethyst St.) City Funded Design A Lakeshore-LakeVista $7,571,385.00 Fall 2015 Fall 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW023 Carondelet St. (Canal St - US 90) City Funded Complete B Central Business District $941,878.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable,installation of ADA  ramps.
DPW024 Carrollton Ave  (St. Charles - Claiborne US 90) City Funded Complete A Mid-City $3,439,548.00 11-Jan-10 A 14-Jul-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps and bikelane striping &  signage.
DPW027 Carrollton Ave & Palmetto / Washington Streetscapes City Funded Construction AB Gert Town $500,000.00 28-May-13 A 03-Oct-13 A An enhancement project that may include: New road striping, improved curbs,  gutters and sidewalks, improvements to drainage and catch basins, installation  of new landscaping and streetlights.
DPW025 Carrollton Ave (South) (I-10 - Claiborne US 90) City Funded Complete AB Mid-City $3,520,481.00 11-Jan-10 A 14-Jul-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, renewal & replacement of  sidewalks, installation of ADA ramps.
DPW234 Carrollton Intersection (S. Carrollton Ave. from I-10 - Palm St.) City Funded Construction AB Gert Town $1,500,000.00 28-May-13 A 03-Oct-13 A Traffic signal and roadway intersection improvements
DPW029 Cartier Ave  (Mirabeau Ave - Filmore Ave) City Funded Awaiting Bond Sale D Filmore $2,683,932.00 Spring 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
PWF074 Catchbasin/Manhole Repair City Funded Complete ABCDE City Wide $6,891,414.00 30-Jun-08 A 08-Aug-10 A Repair of catchbasins and manholes damaged as a direct result of  post-Hurricane Katrina clean-up efforts.
DPW030 Catina (Mouton - Robert E Lee), Louisville (Filmore - Robert E Lee) City Funded Complete A Lakeview $5,339,372.00 22-Mar-10 A 10-Jan-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW034 Cherokee St (Hampson St - Freret St) City Funded Bid & Award A East Carrollton $1,402,431.00 Spring 2014 Fall 2014 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW365 City Park Ave. (Canal - Orleans) PTP Complete A Mid-City $1,244,264.00 04-Mar-13 A 24-Jun-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW036 City Park Tad Gormley Parking Lots (Marconi - Stadium Dr.) City Funded Design A City Park $930,660.00 Summer 2014 Fall 2014 New parking area at Tad Gormley Stadium and expand parking area at Marconi  Drive.
DPW178 Claiborne (South) @ Toledano (Napoleon Ave - Martin  Luther King  Jr.) City Funded Construction B Central City $2,174,840.00 23-Jul-12 A 04-Dec-13 A An enhancement project that may include: A new memorial commemorationg the  contributions of nine New Orleans Civil Rights Leaders, palm tree lined walkways  from Jackson Ave to Josephine St, Lighting and landscaping in the median from  Napoleon Ave to Jackson Ave, new streetlights complete with fixtures on which to  hang decorative banners.
DPW089 Claiborne Avenue Streetscape (Cleveland St. - Gravier St.) City Funded Complete B Central Business District $2,508,055.00 04-Jan-10 A 17-Sep-10 A Sidewalk and landscaping  improvements
DPW041 Common St. (Loyola Ave - S. Peters St) City Funded Complete B Central Business District $1,236,691.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bikelane signage &  striping
DPW377 Congress St. (Hayne - Madrid) PTP Bid & Award D Pontchartrain Park $487,964.00 Early Winter  2014 Spring 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW378 Congress St. (Madrid - Chef Menteur) PTP Bid & Award D Gentilly Woods $1,476,057.00 Early Winter  2014 Spring 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW382 CostCo Infrastructure Improvements City Funded Construction AB Gert Town $2,102,320.00 29-Apr-13 A 03-Oct-13 A An enhancement project that may include: Demolition of existing frontage  roads, installation of road grading, new road striping, improved curbs,  gutters and sidewalks, improvements to drainage and catch basins,   construction of a deceleration lane on Palmetto St, warning beacons at  the Pontchartrain Expressway exit from I-10, new traffic signal at Dixon St and  Dublin St., and installation of new landscaping and  streetlights.
DPW285 Countdown Timers - Downtown City Funded Design B Central Business District $331,894.00 Spring 2015 Summer 2015 Retrofit existing traditional  walk/stop pedestrian signals with countdown timers and adding new pedestrian  countdown signals in the Downtown area.
DPW286 Countdown Timers - Poydras City Funded Design B Central Business District $545,000.00 Spring 2015 Summer 2015 Retrofit existing traditional  walk/stop pedestrian signals with countdown timers and adding new pedestrian  countdown signals along Poydras.
DPW250 Crowder Blvd (Dwyer Rd - US 90) Bikeway City Funded Complete E Read Blvd West $9,600.00 08-Dec-09 A 01-Jul-10 A Install  new pavement markings and signage
DPW368 Dauphine St. (Canal - Esplanade) PTP Complete C French Quarter $1,322,195.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW372 Decatur St. (St Louis - Dumaine) PTP Complete C French Quarter $599,038.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW045 DeSaix Bridge over Bayou St. John City Funded Planning AD City Park $1,289,231.00 #N/A #N/A Bridge reconstruction
DPW403 Downman Rd (Babylon - Odin) PTP Design D Pines Village $412,500.00 Spring 2014 Fall 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW048 Downtown  Bike Rack Installation Project City Funded Design B Central Business District $275,994.00 Spring 2015 Spring 2015 Installation of bike racks in various  locations.
DPW392 Downtown Infrastructure Improvements (Dorsiere, Iberville, Julia St) City Funded Construction BC Central Business District $6,500,000.00 24-Jul-13 A Early Winter 2014 The scope of work in the French Quarter includes resurfacing Dorsiere St.  from Iberville to Canal streets, and Iberville St. from North Peters to North  Rampart streets with concrete. These additional infrastructure improvements will  include new Americans with Disabilities Act-compliant curb ramps, repairs to  damaged sidewalks and driveway aprons, drainage point repairs, new striping and  crosswalks, repairs to damaged street lights including conversion of  non-historic streetlights to LED lights, signage improvements, and improved  sanitation practices.   The scope of work in the CBD includes resurfacing Julia St. from Convention  Center Blvd. to Loyola Ave. with concrete. These additional infrastructure  improvements will include new sidewalks and driveway aprons, Americans with  Disabilities Act-compliant curb ramps, drainage point repairs, new striping and  crosswalks, signage improvements, and improved sanitation practices.
DPW287 Dr. Charles R. Drew Elementary - Safe Routes to School (K08-572) State ID 737-99-1024 City Funded Design C Bywater $343,334.00 Spring 2014 Summer 2014 Construct curb extensions with ADA compliant ramps at 16  locations, countdown pedestrian signals at 6 locations, pavement markings for  crosswalks at 16 locations, and miscellaneous markings and signs all in the  immediate vicinity of the Dr. Charles R. Drew Elementary School.  State  Project No. 737-36-0015 and Federal Project No. SRS-3608 (504).
DPW379 Drain and Catchbasin Cleanout due to Hurricane Issace City Funded Complete ABCDE City Wide $6,000,000.00 07-Sep-12 A 09-Nov-12 A #N/A
DPW321 Drain Point Repair Services City Funded Complete ABCDE City Wide $6,016,300.00 22-Feb-10 A 01-Oct-11 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
DPW293 Drainage Master Plan Study City Funded Complete ABCDE City Wide $2,000,000.00 #N/A 30-Apr-12 A Conduct field investigations and survey of major drainage  facilities.  Review and update existing Geographic Information System (GIS)  data.  Review and assess current data management, develop model for  new system.  Develop standards and guidelines, and maintenance  procedures.
DPW050 Earhart Blvd Segment I (Hamilton St - Fern St) City Funded Complete AB Gert Town $12,732,296.00 30-Nov-09 A 10-Oct-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW329 Edgelake Court (Crowder Rd - Hayne Blvd) City Funded Complete D Little Woods $338,900.00 08-Apr-13 A 29-May-13 A Asphalt pavement, base repair and  curb replacement.
DPW052 Elysian Fields (Lakeshore Dr. - Gentilly Blvd. / US 90) City Funded Complete D Gentilly $1,597,583.00 20-Nov-09 A 12-Apr-12 A Rehabilitation of roadway by milling existing surface and overlay with new  asphalt, including pre-milling patching repairs as well as adjustment of utility  manholes, where applicable, removal & replacement of concrete roadway from  Lakeshore Dr. - Robert E Lee Blvd, removal & replacement of sidewalk,  installation of ADA ramps, bike lane striping & signange.
DPW314 Esperanza Charter School - Safe Routes to School (K09-886)  State ID 737-99-1024 City Funded Design A Mid-City $304,956.00 Spring 2014 Summer 2014 Construct 16 curb extensions, sidewalk repair, 2 bike  racks, pavement markings, countdown pedestrian signals and signs near the  Esperanza Charter School.  State Project No. 737-36-0022 and Federal  Project No. SRS-3609 (509).
DPW396 Esplanade Ave (Claiborne - N.Rampart) Bikeway City Funded Construction C Treme - Lafitte $13,000.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW366 Esplanade Ave. (Moss - N. Claiborne) PTP Complete AC Treme - Lafitte $3,019,171.00 04-Mar-13 A 24-Jun-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW369 Esplanade Ave. (N Rampart - N Peters) PTP Complete C French Quarter $1,602,028.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW055 Filmore Ave (Bayou St. John - Elysian Fields Ave) City Funded Complete D Filmore $2,743,221.00 20-Nov-09 A 31-May-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalk, installation of ADA ramps, bike lane striping &  signage.
DPW352 Filmore Ave. (Marconi - Wisner) PTP Complete A City Park $512,344.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW351 Filmore Ave. (West End - Canal) PTP Complete A Lakeview $512,344.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW056 Filmore Bridge over Bayou St. John City Funded Planning AD City Park $1,050,000.00 #N/A #N/A Bridge  reconstruction
DPW058 Fleur de Lis Phase II (Veterans Blvd - Harrison Ave) City Funded Complete A West End $11,976,162.00 10-Dec-09 A 04-Mar-11 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW059 Fleur de Lis Phase III (30th - Hammond Hwy) City Funded Design A West End $11,463,286.00 Early Winter 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW359 Fontainebleau Dr. (Broadway - Nashville) PTP Construction AB Marlyville & Fontainbleau $439,152.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW340 Forstall St. (Douglass St. - N. Claiborne) PTP Complete E Lower Ninth Ward $677,527.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW266 Franklin Ave. ( I-610 - LA 46) Bikeway City Funded Design CD St. Claude $24,000.00 Early Winter  2014 Early Winter 2014 Install  new pavement markings and signage
DPW350 Franklin Ave. (Filmore - Gentilly) PTP Complete D Gentilly Terrace $1,451,625.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW063 Freret St Streetscape (Napoleon Ave  - Jefferson Ave) City Funded Construction B Freret $1,000,000.00 04-Nov-13 A Spring 2014 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW357 Freret St. (Louisiana - Jefferson) PTP Construction B Freret $1,375,469.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW278 Galvez ( Elysian Fields - Orleans Ave ) Bikeway City Funded Design D Treme - Lafitte $24,000.00 Fall 2014 Late Winter 2014 Install  new pavement markings and signage
DPW066 Galvez (Poydras - Orleans Ave.) PTP Complete ACD Mid-City $808,999.00 27-Feb-10 A 30-Jun-11 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW068 Gardena Dr (St. Bernard Ave - Paris Ave.) City Funded Planning D Filmore $3,890,100.00 Spring 2016 Summer 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW389 General DeGaulle Dr (Woodland - Holiday) PTP Design C Old Aurora $1,508,000.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW389 General DeGaulle Dr (Woodland - Holiday) PTP Design C Old Aurora $1,508,000.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW054 General Meyer Ave Streetscape (Hendee St - Odeon Ave) City Funded Design C Behrman $584,906.00 Summer 2014 Fall 2014 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW349 Gentilly Blvd. (Paris - Broad) PTP Construction AD Fairgrounds $2,415,337.00 01-Jun-13 A 17-Oct-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW070 Gentilly Minor Streets - Caton (Gentilly Blvd. - Norman Mayer Ave.), Touro (Caton - Senate) City Funded Construction D Dillard $460,367.00 16-Sep-13 A Late Winter 2013 Improvements to various  minor streets, which may include reconstruction and/or milling and overlay.
DPW071 Gentilly Streetscape (Caton, Gentilly, Elysian Fields) City Funded Construction D Dillard $684,567.00 18-Nov-13 A Early Winter 2014 May include sidewalk or other pedestrian walkway improvements, bikeways, traffic  and pedestrian signage or signalization, landscaping, lighting, or public art.
DPW272 Girod St.  ( Loyola Ave - S. Peters St)  Bikeway City Funded Complete B Central Business District $14,000.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW074 Girod St. (Loyola Ave - S. Peters St) City Funded Complete B Central Business District $870,959.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW075 Gordon (Chartres - St. Claude), Flood (Peters - St. Claude) City Funded Complete E Lower Ninth Ward $6,254,075.00 01-Apr-11 A 01-Jun-12 A Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW076 Gravier St (Galvez - Broad) City Funded Awaiting Bond Sale B Tulane - Gravier $2,586,888.00 Spring 2016 Summer 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW077 Gravier St. (Loyola Ave - S. Peters St) City Funded Complete B Central Business District $585,378.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW081 Harrison Ave Bridge over Bayou St. John (Eastbound) City Funded Complete AD City Park $709,610.00 06-Apr-10 A 03-Oct-11 A Bridge  reconstruction
DPW082 Harrison Ave Bridge over Bayou St. John (Westbound) City Funded Complete AD City Park $709,610.00 06-Apr-10 A 03-Oct-11 A Bridge reconstruction
DPW083 Harrison Ave Streetscape (Canal St - Orleans Ave) City Funded Construction A Lakeview $3,554,499.00 18-Mar-13 A Spring 2014 An enhancement project that may include: Additional trees and shrubbery, new  brick-paved sidewalks, additional lighting, fresh crosswalk markings, and  improved irrigation.
DPW253 Harrsion Ave ( West End Blvd- Orleans Canal) Bikeways City Funded Design A Lakeview $30,100.00 Spring 2014 Spring 2014 Install  new pavement markings and signage
DPW344 Hayne Blvd. (Press - Congress) PTP Complete D Pontchartrain Park $480,958.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW085 Holiday Dr  (General Meyer Ave - MacArthur) City Funded Complete C Old Aurora $3,186,173.00 01-Jun-11 A 07-Feb-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW086 Holiday Dr (MacArthur - Behrman) City Funded Complete C Old Aurora $2,732,303.00 15-Nov-11 A 16-Feb-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW245 Holy Cross Roadway Improvements - Douglass St., Andry St., N. Peters St. City Funded Complete E Lower Ninth Ward $884,332.00 11-Jan-10 A 12-Oct-10 A Improvements to various  minor streets, which may include reconstruction and/or milling and overlay.
DPW087 Homedale (Canal - West End), Center (33rd - Tacoma), Milne (Homedale - Florida), Walker (Marshal-Orl City Funded Design A Lakeview $10,890,537.00 Spring 2015 Early Winter 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW088 Howard Avenue Ext. (Loyola Ave  - LaSalle St) City Funded Design B Central Business District $6,762,202.00 Fall 2014 Early Winter 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW243 Huntlee Dr. (General  DeGaulle - Berkley Dr) City Funded Bid & Award C Old Aurora $1,572,560.00 Spring 2015 Fall 2015 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW315 International School of LA - Safe Routes to School State ID 737-99-1024 City Funded Design B Lower Garden District $259,624.00 Spring 2014 Summer 2014 Construct curb extensions with ADA compliant ramps at  various locations, install countdown pedestrian signals, pavement markings for  crosswalks at various locations, and miscellaneous markings and signs all in the  immediate vicinity of the International School of LA.  State Project No.  737-36-0019.
DPW090 Jackson Ave (Claiborne Ave - Galvez St) City Funded Design B Central City $3,032,008.00 Spring 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities
DPW283 Jefferson Ave. (Caliborne - Tchoupitoulas ) Bikeway City Funded Design A Audubon $12,750.00 Early Winter  2014 Early Winter 2014 Install  new pavement markings and signage
DPW092 Johnson St (Jefferson - Claiborne), Melodia (Claiborne - S. Johnson), Octavia (Freret - Claiborne) City Funded Design A Audubon $5,864,700.00 Fall 2015 Fall 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW094 Lafitte Greenway/Lafitte GW Corr. Bikepath-(N. Alexander- Basin) City Funded Bid & Award A Treme - Lafitte $7,772,000.00 Early Winter  2014 Spring 2015 Includes sidewalk and pedestrian  walkway improvements, bikeways, traffic and pedestrian signage, landscaping,  lighting, and public art.
DPW097 Lake Forest Ave. Traffic Improvements  (Lake Forest at Bullard) City Funded Planning E New Orleans East $151,050.00 Fall 2014 Early Winter 2015 Roundabout Evaluation
DPW096 Lake Forest Blvd. Widening (Eastover Dr - I-510) City Funded Design E Read Blvd East $2,202,360.00 Summer 2014 Summer 2015 Widening of existing roadway,  including the replacement of affected utilities.
DPW098 Lakefront/Holy Cross Traffic Signals City Funded Complete A Holy Cross $3,415,290.30 17-Jan-12 A 08-Mar-13 A Traffic signal  improvements
DPW100 LaSalle St (Poydras - Tulane Ave US 61) City Funded Complete B Uptown $741,349.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW101 LeBoeuf (Patterson - Opelousas), Sumner (Newton - Opelousas), Slidell (Whitney - Sumner) City Funded Complete C U.S. Naval Base $4,648,674.00 07-Feb-11 A 22-Dec-11 A Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW102 Leon C. Simon Dr (London Canal - Elysian Fields Ave) City Funded Complete D Lake Terrace and Oaks $1,208,379.00 20-Nov-09 A 18-Apr-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps,  bike lane striping & signage.
DPW360 Leonidas St. (Palmetto - Earhart) PTP Complete A Hollygrove $426,936.00 17-Apr-13 A 22-Aug-13 A Removal  and replacement of the sidewalk intersections for the installation of the  compliant ADA ramps and the installation of the ADA ramps in the  medians.
DPW282 Louisiana Ave ( St. Charles - Magazine) Bikeway City Funded Design B Touro $14,000.00 Early Winter  2014 Early Winter 2014 Install  new pavement markings and signage
DPW292 Lower Ninth Ward Pilot Streets - Make It Right City Funded Complete E Lower Ninth Ward $3,070,608.00 11-Jun-12 A 24-Sep-12 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW106 Lower Ninth Ward Streetscape Phase I (N. Claiborne - Andry to Lamanche)(St. Claude-Bridge to Egania) City Funded Complete E Lower Ninth Ward $1,244,251.95 01-Jun-12 A 18-Nov-12 A An enhancement project that may include: Sidewalk  and ADA-compliant curb ramps, landscaping, lighting, public art space,  and minor utility modifications and improvements.
DPW393 Lower Ninth Ward Streetscape Phase II (N. Claiborne -  Lamanche - Tennessee) City Funded Design E Lower Ninth Ward $655,748.05 Spring 2014 Summer 2014 An enhancement project that may include: Sidewalk  and ADA-compliant curb ramps, landscaping, lighting, public art space,  and minor utility modifications and improvements.
DPW108 Loyola Ave. (Canal St. - US 90) City Funded Complete B Central Business District $3,584,539.00 03-Nov-09 A 04-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW113 Magazine St. (Canal - US 90) City Funded Complete B Central Business District $1,066,407.00 03-Nov-09 A 25-Aug-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalks, installation of trees, ADA ramps, bike lane striping &  signage.
DPW110 Magazine St. (St. Joseph St - Calliope St) City Funded Complete B Central Business District $4,938,363.00 29-Jun-09 A 13-May-10 A Sidewalk and landscaping  improvements
DPW114 Magazine St. (US 90B - Nashville) City Funded Complete AB Uptown $3,373,617.00 04-Jan-11 A 10-Nov-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps  including  street names and bikelane striping & signage, removal &  replacement of sidewalks.
DPW112 Magazine St. Phase I (Nashville Ave - Calhoun St) City Funded Design A Audubon $4,708,135.00 Fall 2014 Fall 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW111 Magazine St. Phase II (Calhoun - Leake Ave) City Funded Design A Audubon $7,846,892.00 Summer 2015 Summer 2016 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW391 Magnolia Converted Ped Bridge City Funded Planning C Bayou St. John $810,000.00 Early Winter 2015 Spring 2015 Bridge reconstruction
DPW249 Marconi Blvd. (Robert E. Lee - Norfolk Southern Railroad) Bikeways City Funded Complete AC City Park $24,750.00 08-Dec-09 A 16-Jun-10 A Install  new pavement markings and signage
DPW118 Martin Bridge over Morrison City Funded Complete D Little Woods $1,188,700.00 02-Nov-11 A 28-Jun-12 A Bridge  reconstruction
DPW263 Martin Luther King  Blvd ( Caliborne Ave - Broad St ) Bikeway City Funded Complete B B. W. Cooper $24,850.00 22-Aug-13 A 17-Oct-13 A Install  new pavement markings and signage
DPW395 Martin Luther King Blvd (Washington - Earhart) Bikeway City Funded Construction B Gert Town $4,000.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW346 Mayo Rd. (Hayne - Morrison) PTP Complete D Little Woods $601,198.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW347 Mayo Rd. (Morrison - I-10) PTP Complete D Little Woods $360,719.00 03-Aug-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW397 Mercedes St (MacArthur - Herschel) PTP Design C Behrman $232,000.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW120 Michoud Blvd (Chef Menteur Blvd - Dwyer Rd) City Funded Awaiting Bond Sale E Village de Lest $3,229,676.00 Summer 2014 Late Winter 2014 Removal of existing roadways and replace with new hot mix asphalt  roadways including new concrete curb and gutter bottom, rehabilitation of water  and drain lines, constructing driveways, sidewalks and handicap ramps, and all  work incidental to the project as shown on the plans or as directed by the  Engineer in the field.   The width of 2 new road ways is 20 ft.  each Total project length is 1,840 ft.   The total reconstruction shall include replacement of subsurface  utilities which includes:   2,600 ft. of new  water lines, 2,180 ft. of new sewer lines and 2,140 ft. of new concrete drain pipes with new catch basins &  new manholes.
DPW142 Michoud Front Door Infrastructure Improvements (Old Gentilly Road from I-510 - Chef Menteur Highway) City Funded Bid & Award E Viavant $6,253,798.00 Spring 2014 Fall 2014 An enhancement project that may  include: Construction of both new asphalt, and concrete roadways and appropriate  striping, repair of existing roadways, landscaping, install and improved  lighting, improved drainage, and intersection improvements at  Chef Menteur and Almonaster Blvd.
DPW128 Mirabeau Ave (Bayou St. John - Elysian Fields Ave) City Funded Complete D Filmore $2,950,864.00 20-Nov-09 A 02-May-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & replacement of  sidewalk, installation of ADA ramps, bike lane striping &  signage.
DPW277 Miro St ( Elysian Fields Ave - Orleans Ave) Bikeway City Funded Complete ACD Seventh Ward $24,450.00 22-Aug-13 A 17-Oct-13 A Install  new pavement markings and signage
DPW129 Miro St (Elysian Fields Ave - Orleans Ave) City Funded Complete ACD Mid-City $978,426.00 04-Jan-10 A 16-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW345 Morrison Rd. (Lamb - Mayo) PTP Complete D Little Woods $961,917.00 16-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW373 N Peters St. (Canal - St Louis) PTP Complete C French Quarter $1,200,219.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW067 N. Galvez  St (Elysian Fields Ave  - Almonaster Ave ) City Funded Awaiting Bond Sale D St. Roch $5,259,425.00 Spring 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW289 N. Galvez (Orleans Ave. - Poydras) City Funded Complete AB Mid-City $3,309,167.00 04-Jan-10 A 16-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable  installation of ADA  ramps.
DPW130 N. Galvez St (Tennessee St  - Delery St) City Funded Awaiting Bond Sale E Lower Ninth Ward $7,891,800.00 Spring 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW238 Napoleon, Broad and Fontainebleau Intersection Design City Funded Complete B Broadmoor $250,000.00 #N/A #N/A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW290 Napoleon-Freret Roadway Improvements (Clara St. (Napoleon - Cadiz), Jena (Clara - S. Claiborne)) City Funded Complete B Freret $855,300.00 11-Feb-11 A 14-Oct-11 A Improvements to various minor streets,  which may include reconstruction and/or milling and overlay.
DPW284 Nashville Ave (Caliborne US 90 - Tchoupitoulas) Bikeway City Funded Complete A Audubon $14,250.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW131 Nashville Ave (Claiborne US 90 - Magazine St ) (Magazine St - Tchoupitoulas St) City Funded Complete A Uptown $5,429,536.00 09-Nov-09 A 16-Dec-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, removal & relpacement of  sidewalks &  installation of ADA ramps.
DPW358 Nashville Ave. (S.Claiborne - Fountainbleau) PTP Construction A Marlyville & Fontainbleau $622,132.00 23-Aug-13 A 06-Nov-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW279 Navarre Ave ( Canal Blvd - Marconi Dr) Bikeway City Funded Construction A City Park $7,200.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW132 Navarre Ave. (Canal Blvd. - Marconi Dr) City Funded Complete A Lakeview $808,592.00 04-Jan-10 A 16-Nov-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW239 New Orleans East Streetscape Improvements (Read Blvd, Lakeforest Blvd, Crowder Rd) City Funded Complete E New Orleans East $3,000,000.00 19-Apr-12 A 14-Jun-13 A An enhancement project that may  include: New sidewalks along Lake Forest Blvd, with access to the New Orleans  East Regional Library and Joe Brown Park, new seating and trach receptacles at a  small park at the corner of Lake Forest and Wright Rd, installing a new walking  path on Lake Forest Blvd from Wright Rd to Read Blvd, Adding about 140  additional lights and more that 30 new trees,  and developing a dedicated bike lane on Read Blvd,  Crowder Blvd and Lake Forest Blvd.
DPW137 New Orleans Museum District Enhancement City Funded Bid & Award B Central Business District $334,385.00 Early Winter  2014 Summer 2014 An enhancement project that may  include: Removal and replacement of concrete curbs, walkways, gutters, and  driveways, installation of new brick sidewalks, removal and replacement of  asphalt pavement, adjustment of manholes, catch basins and in-ground utility bases, installation of new ADA-compliant  ramps at corners, planting new plants. trees and tree  grates.
DPW390 Newton St (Whitney - Behrman) PTP Design C Whitney $1,059,700.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW390 Newton St (Whitney - Behrman) PTP Design C Whitney $1,059,700.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW387 Newton St (Whitney - Teche) PTP Design C Whitney $1,549,200.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW402 North Galvez (Orleans - Elysian Fields Ave) PTP Design C Seventh Ward $2,777,300.00 Spring 2014 Fall 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW144 Old Spanish Trail (Nighthart St - Sherwood Dr) City Funded Awaiting Bond Sale E Read Blvd East $2,321,916.00 Early Winter 2016 Spring 2016 Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW322 Opelousas Street Extension (Behrman Avenue to O'Bannon St.) City Funded Complete C Algiers Point $2,180,232.00 11-Feb-11 A 27-Jun-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW140 Oretha Castle Haley Blvd Streetscape (St. Andrew St. - Calliope St.) City Funded Design B Central City $965,000.00 Spring 2014 Summer 2014 An enhancement project that may  include: Removal of the median between Felicity St and Martin Luther King Blvd,  larger pedestrian crossings/medians at intersections, installation of new  ADA-compliant ramp curbs, repairs to damaged sidewalks, conversion of the  roadway from two travel lanes  and parking lane into a parking lane, bicycle lae  and travel lane in each direction.
DPW145 Orleans Ave. (N. Claiborne Ave - City Park Ave.) City Funded Complete A Mid-City $4,437,504.00 04-Jan-10 A 01-Oct-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW388 Pace Blvd (Gen Meyer Ave - Wall Blvd) PTP Design C Behrman $1,084,700.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW388 Pace Blvd (Gen Meyer Ave - Wall Blvd) PTP Design C BRMN $1,305,000.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW147 Paris Ave. (I-610 - Mirabeau Ave) City Funded Complete D St. Bernard Area $742,125.00 20-Nov-09 A 16-Apr-12 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, Concrete panel replacement,  removal & replacement of sidewalks, installation of ADA ramps, bike lane  striping & signage.
DPW150 Park Island Bridge over Bayou St. John City Funded Complete AD Filmore $2,085,853.00 08-Dec-09 A 01-Jun-11 A Bridge  reconstruction
PWF006 Patching Repairs - City Park FEMA Phase I Complete A City Park $366,217.00 17-May-10 A 22-Nov-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF013 Patching Repairs - Filmore FEMA Phase I Complete D Filmore $2,181,931.00 15-Feb-10 A 03-Aug-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF018 Patching Repairs - Gentilly Woods FEMA Phase I Complete D Gentilly Woods $521,674.00 06-Jul-10 A 10-Sep-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF023 Patching Repairs - Lake Terrace & Oaks FEMA Phase I Complete D Lake Terrace and Oaks $746,569.00 30-Aug-10 A 15-Dec-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF024 Patching Repairs - Lakeshore - Lake Vista FEMA Phase I Complete A Lakeshore-LakeVista $957,181.00 15-Mar-10 A 27-Aug-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF025 Patching Repairs - Lakeview FEMA Phase I Complete A Lakeview $7,532,380.00 14-Apr-09 A 22-Jul-10 A Patching repairs of streets and sidewalks damaged by storm waters and debris  removal.
PWF026 Patching Repairs - Lakewood FEMA Phase I Complete A Lakewood $587,728.00 17-Aug-09 A 03-Jun-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF030 Patching Repairs - Lower Ninth Ward FEMA Phase I Complete E Lower Ninth Ward $2,846,167.00 23-Mar-09 A 04-Feb-11 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF032 Patching Repairs - Marlyville & Fontainebleau FEMA Phase I Complete AB Marlyville & Fontainbleau $3,549,801.00 14-Jun-10 A 10-Dec-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF034 Patching Repairs - Milan & Touro Neighborhoods FEMA Phase I Complete B Milan & Touro Neighborhoods $693,338.00 05-Apr-10 A 15-Jul-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF035 Patching Repairs - Milneburg FEMA Phase I Complete D Milneburg $3,926,742.00 02-Oct-09 A 23-Jul-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF036 Patching Repairs - Navarre FEMA Phase I Complete A Navarre $870,164.00 23-Aug-10 A 07-Jan-11 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF039 Patching Repairs - Pines Village FEMA Phase I Complete D Pines Village $925,794.00 26-Apr-10 A 20-Jul-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF043 Patching Repairs - Read Blvd West FEMA Phase I Complete E Read Blvd West $2,235,635.00 03-Aug-09 A 12-May-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF049 Patching Repairs - Treme - Lafitte FEMA Phase I Complete AC Treme - Lafitte $2,784,704.00 01-Dec-09 A 17-May-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF051 Patching Repairs - Uptown & West Riverside FEMA Phase I Complete AB Uptown & West Riverside $1,048,260.00 02-Nov-09 A 06-May-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
PWF053 Patching Repairs - West End FEMA Phase I Complete A West End $1,789,466.00 26-Oct-09 A 10-Dec-10 A Patching repairs of streets and  sidewalks damaged by storm waters and debris removal.
DPW323 Patterson Drive Extension Phase 1 (Hendee St. to Heerman St) City Funded Complete C Old Aurora $1,052,202.00 03-Dec-12 A 13-May-13 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW380 Patterson Drive Extension Phase 2 Heerman St to O'Bannon St.) City Funded Bid & Award C Old Aurora $550,000.00 Spring 2014 Summer 2014 Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable.
DPW158 Poydras St (Carondelet St - Camp St) City Funded Complete B Central Business District $129,243.00 03-Nov-09 A 25-Aug-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, lakebound, Camp- St Charles  only.
DPW159 Poydras St (LaSalle St  - Loyola Ave) City Funded Complete B Central Business District $106,042.00 03-Nov-09 A 25-Aug-10 A Installation of compliant ADA ramps, Bike lane striping  & signage.
DPW255 Press Dr( US 90 - Robert E Lee Blvd ) Bikeway City Funded Complete D Gentilly Woods $20,400.00 08-Dec-09 A 16-Jun-10 A Install  new pavement markings and signage
DPW233 Press Drive Streetscape  (Chef - Leon C Simon) City Funded Construction D Pontchartrain Park $245,996.00 19-Apr-12 A Late Winter 2013 An enhancement project that may include: Planting more  than 250 trees and over 533 shrubs on the median from Chef Menteur Hwy to Leon  C. Simon Blvd, installing neighborhood signage at Press Dr, as well as signs  denoting the Gentilly Woods and Pontchartrain Park Neighborhoods.
DPW166 Rampart St (Canal Blvd - Elysian Fields Ave) PTP Planning C Central Business District $656,732.00 #N/A #N/A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW356 Rampart St. (Esplanade - Elysian Fields) PTP Bid & Award C Seventh Ward $1,036,904.00 Spring 2014 Fall 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW355 Rampart St. (Iberville - Esplanade) PTP Bid & Award C French Quarter $1,659,037.00 Spring 2014 Fall 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
PWF159 Recovery Program - Algiers Point FEMA Phase II Design C Algiers Point $494,486.85 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF128 Recovery Program - Audubon FEMA Phase II Planning A Audubon $354,742.03 Fall 2016 Fall 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF142 Recovery Program - B.W. Cooper FEMA Phase II Planning B B. W. Cooper $1,315,502.24 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF140 Recovery Program - Bayou St. John/Fairgrounds FEMA Phase II Planning AC Fairgrounds/Bayou St. John $1,292,155.52 Spring 2016 Spring 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF160 Recovery Program - Behrman FEMA Phase II Design C Behrman $2,091,273.06 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF165 Recovery Program - Black Pearl FEMA Phase II Planning A Black Pearl $2,052,405.54 Fall 2016 Fall 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF100 Recovery Program - Broadmoor FEMA Phase II Design AB Broadmoor $4,687,467.40 Late Winter 2014 Late Winter 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF120 Recovery Program - Bywater/Marigny FEMA Phase II Design CD Marigny & Bywater Neighborhoods $675,868.30 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF139 Recovery Program - Central City FEMA Phase II Planning B Central City $5,244,840.89 Spring 2016 Spring 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF126 Recovery Program - City Park FEMA Phase II Design A City Park $398,317.13 Early Winter 2015 Early Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF136 Recovery Program - Desire Area Development FEMA Phase II Planning E Desire Area $888,894.81 Early Winter 2016 Early Winter 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF123 Recovery Program - Dillard FEMA Phase II Design D Dillard $1,978,667.55 Summer 2015 Summer 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF138 Recovery Program - Dixon FEMA Phase II Planning A Dixon $2,909,680.47 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF164 Recovery Program - East Carrollton FEMA Phase II Planning A East Carrollton $6,073,168.14 Fall 2016 Fall 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF141 Recovery Program - East Riverside, Garden District, Irish Channel, St. Thomas Dev, Village De L'Est FEMA Phase II Planning E Village de Lest $8,220,120.30 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF112 Recovery Program - Filmore Quadrant 1 FEMA Phase II Design D Filmore $6,430,889.75 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF113 Recovery Program - Filmore Quadrant 2 FEMA Phase II Design D Filmore $4,877,775.15 Early Winter 2015 Early Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF146 Recovery Program - Fisher Development FEMA Phase II Design C Fisher Development $18,042.47 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF119 Recovery Program - Florida Area/Florida Development FEMA Phase II Design D Florida Area/Fischer Dev./Florida Dev. $3,648,193.91 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF132 Recovery Program - French Quarter FEMA Phase II Planning C French Quarter $0.00 Late Winter 2014 Late Winter 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF127 Recovery Program - Freret FEMA Phase II Design B Freret $453,135.46 Spring 2016 Spring 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF137 Recovery Program - Gentilly Terrace FEMA Phase II Planning D Gentilly Terrace $9,569,406.16 Early Winter 2016 Early Winter 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF133 Recovery Program - Gentilly Woods FEMA Phase II Design D Gentilly Woods $2,001,823.90 Fall 2015 Fall 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF151 Recovery Program - Gert Town FEMA Phase II Planning AB Gert Town $2,710,797.74 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF143 Recovery Program - Hollygrove FEMA Phase II Planning A Hollygrove $4,759,956.05 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF129 Recovery Program - Holy Cross FEMA Phase II Design CD Holy Cross $822,342.55 Summer 2014 Summer 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF131 Recovery Program - Iberville/ Tulane Gravier FEMA Phase II Design BC Tulane/Gravier/Iberville Neighborhoods $500,184.67 Late Winter 2014 Late Winter 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF125 Recovery Program - Lake Terrace & Oaks FEMA Phase II Design D Lake Terrace and Oaks $1,375,706.16 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF168 Recovery Program - Lake Vista FEMA Phase II Design A Lakeshore-LakeVista $5,296,776.82 Fall 2014 Summer 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF107 Recovery Program - Lakeshore FEMA Phase II Design A Lakeshore-LakeVista $2,415,795.79 Fall 2015 Fall 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF102 Recovery Program - Lakeview - Vicksburg St. Demonstration FEMA Phase II Complete A Lakeview $250,000.00 01-Oct-12 A 03-Dec-12 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF103 Recovery Program - Lakeview Quadrant 1 FEMA Phase II Design A Lakeview $5,937,099.59 Summer 2014 Summer 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF104 Recovery Program - Lakeview Quadrant 2 FEMA Phase II Design A Lakeview $10,411,982.15 Fall 2015 Fall 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF108 Recovery Program - Lakewood FEMA Phase II Design A Lakewood $520,837.64 Summer 2014 Summer 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF163 Recovery Program - Leonidas FEMA Phase II Planning A Leonidas $4,001,864.99 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF115 Recovery Program - Little Woods FEMA Phase II Design DE Little Woods $362,004.24 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF156 Recovery Program - Lizardi St FEMA Phase II Complete E Lower Ninth Ward $727,058.94 08-Apr-13 A 17-Jun-13 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF106 Recovery Program - Lower Garden District/CBD FEMA Phase II Design BC Lower Garden District/Central Business District $276,241.08 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF096 Recovery Program - Lower Ninth Ward (Paving Only - Quad 1 and 3) FEMA Phase II Design E Lower Ninth Ward $6,082,631.93 Summer 2014 Summer 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF157 Recovery Program - Lower Ninth Ward (Paving Only Quad 2) FEMA Phase II Design E Lower Ninth Ward $6,941,623.84 Spring 2014 Spring 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF080 Recovery Program - Lower Ninth Ward Phase II (Deslonde and Flood) FEMA Phase II Construction E Lower Ninth Ward $4,421,392.26 25-Mar-13 A Early Winter 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF093 Recovery Program - Lower Ninth Ward Quadrant 1 FEMA Phase II Design E Lower Ninth Ward $5,944,655.31 Fall 2015 Fall 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF094 Recovery Program - Lower Ninth Ward Quadrant 2 FEMA Phase II Design E Lower Ninth Ward $11,324,902.83 Fall 2015 Fall 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF095 Recovery Program - Lower Ninth Ward Quadrant 3 FEMA Phase II Design E Lower Ninth Ward $7,608,355.49 Early Winter 2015 Early Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF148 Recovery Program - Marlyville-Fontainebleau FEMA Phase II Design AB Marlyville & Fontainbleau $11,029,554.13 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF161 Recovery Program - McDonagh FEMA Phase II Design C McDonogh $66,616.69 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF117 Recovery Program - Mid City FEMA Phase II Design AB Mid-City $7,098,734.42 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF167 Recovery Program - Milan FEMA Phase II Design B Milan $1,557,633.38 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF101 Recovery Program - Milneburg FEMA Phase II Design D Milneburg $2,094,702.41 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF114 Recovery Program - Navarre FEMA Phase II Design A Navarre $565,227.04 Early Winter 2015 Early Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF147 Recovery Program - New Aurora/English Turn FEMA Phase II Planning C New Aurora - English Turn $0.00 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF145 Recovery Program - Old Aurora FEMA Phase II Design C Old Aurora $183,553.38 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF135 Recovery Program - Pines Village FEMA Phase II Design D Pines Village $3,736,112.48 Early Winter 2016 Early Winter 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF110 Recovery Program - Plum Orchard FEMA Phase II Design E Plum Orchard $5,242,813.70 Summer 2016 Summer 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF109 Recovery Program - Pontchartrain Park FEMA Phase II Design D Pontchartrain Park $9,793,873.52 Late Winter 2014 Late Winter 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF105 Recovery Program - Read Blvd East FEMA Phase II Design E Read Blvd East $13,639,040.46 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF134 Recovery Program - Read Blvd West FEMA Phase II Planning E Read Blvd West $5,207,267.84 Spring 2016 Spring 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF130 Recovery Program - Seventh Ward FEMA Phase II Planning ACD Seventh Ward $2,355,123.79 Spring 2016 Spring 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF121 Recovery Program - St. Anthony Quadrant 1 FEMA Phase II Design D St. Anthony $6,644,876.94 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF122 Recovery Program - St. Anthony Quadrant 2 FEMA Phase II Design D St. Anthony $5,192,060.43 Summer 2015 Summer 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF124 Recovery Program - St. Bernard FEMA Phase II Design AD St. Bernard Area $622,314.44 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF099 Recovery Program - St. Claude (Paving Only) FEMA Phase II Design CD St. Claude $8,756,860.07 Spring 2014 Spring 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF082 Recovery Program - St. Claude Phase II Group 1 FEMA Phase II Bid & Award CD St. Claude $3,251,528.00 Early Winter  2014 Summer 2014 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF097 Recovery Program - St. Claude Quadrant 1 FEMA Phase II Design CD St. Claude $2,708,760.58 Late Winter 2015 late Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF158 Recovery Program - St. Claude Quadrant 1- Feliciana St FEMA Phase II Complete CD St. Claude $182,436.25 04-Mar-13 A 23-May-13 A Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF098 Recovery Program - St. Claude Quadrant 2 FEMA Phase II Design CD St. Claude $5,620,189.26 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF111 Recovery Program - St. Roch FEMA Phase II Design CD St. Roch $5,858,994.42 Spring 2015 Spring 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF153 Recovery Program - Tall Timbers-Brechtel FEMA Phase II Design C Tall Timbers - Brechtel $1,036,398.25 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF118 Recovery Program - Touro FEMA Phase II Design B Touro $474,962.74 Spring 2014 Spring 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF150 Recovery Program - Treme - Lafitte FEMA Phase II Design AC Treme - Lafitte $4,492,419.24 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF154 Recovery Program - U.S. Naval Base FEMA Phase II Design C U.S. Naval Base $68,756.52 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF144 Recovery Program - Uptown FEMA Phase II Planning AB Uptown $1,914,167.23 Fall 2016 Fall 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF155 Recovery Program - Venetian Isles FEMA Phase II Design E Venetian Isles $1,036,736.70 Spring 2014 Spring 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF166 Recovery Program - Viavant / Lake Catherine FEMA Phase II Design E Viavant, Lake Catherine, Venetian Isles $1,036,736.70 Summer 2015 Summer 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF116 Recovery Program - West End FEMA Phase II Design A West End $9,258,749.75 Early Winter 2015 Early Winter 2016 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF149 Recovery Program - West Lake Forest FEMA Phase II Design DE West Lake Forest $279,386.52 Fall 2014 Fall 2015 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF152 Recovery Program - West Riverside FEMA Phase II Planning AB West Riverside $792,274.27 Fall 2016 Fall 2017 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
PWF162 Recovery Program - Whitney FEMA Phase II Design C Whitney $1,466,126.95 Spring 2017 Spring 2018 Repair  Hurricane Katrina related infrastructure damage. May include total or partial  replacement of utilities,  sidewalks, American with Disabilities Act-compliant curb ramps, driveway aprons,  curbs and road paving. Visit RecoveryRoads.nola.gov for additional  detail.
DPW320 Reinventing the Crescent Infrastructure Imp. N Peters(St Philip-St Ferdinand)Chartres(Piety-Gallier) City Funded Complete C Marigny & Bywater Neighborhoods $816,508.00 19-Oct-09 A 03-Jun-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of Sidewalks  & ADA ramps.
DPW254 Robert E Lee Blvd ( St. Bernard Ave- Paris Ave) Bikeway City Funded Bid & Award AD Filmore $13,300.00 Early Winter 2014 Spring 2014 Install  new pavement markings and signage
DPW353 Robert E Lee Blvd. (Elysian Fields - Franklin) PTP Complete D Milneburg $1,036,904.00 17-Jun-13 A 19-Sep-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW317 Robert E. Lee (Paris to Pratt) City Funded Complete A Filmore $3,080,990.00 02-Nov-09 A 05-May-10 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW241 Robert E. Lee Blvd (Perlita Dr - Chatham Dr) and Paris Ave. (Robert E. Lee - Aviators) Streetscape City Funded Construction D Filmore $500,000.00 12-Aug-13 A Late Winter 2013 An enhancement project that may include: Installation of new sidewalks and  drivewa aprons, installation of ADA-complaint ramps at sidewalk corners, new  bicycle lane striping, fresh crosswalk and pavement striping, new landscaping  including planting of about 75 trees, new neighborhood signage and lighting, and  improved drainage.
DPW173 Robert E. Lee over London Avenue Canal City Funded Planning AD City Park $1,600,000.00 #N/A #N/A Bridge reconstruction
DPW374 Royal St. (Canal - Esplanade) PTP Complete C French Quarter $1,583,942.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW386 S Peters St (Canal - Calliope St) PTP Design C Central Business District $1,294,920.00 Spring 2014 Summer 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW264 S. Galvez Street ( Earhart- Toledano) Bikeway City Funded Design B Broadmoor $9,300.00 Early Winter  2014 Early Winter 2014 Install  new pavement markings and signage
DPW179 S. Galvez Street (Earhart - Toledano) PTP Design B Central City $510,264.00 #N/A #N/A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW176 S. Jeff. Davis (M. L. King Jr. - Howard) City Funded Complete B Gert Town $1,902,747.00 10-Oct-11 A 30-Mar-12 A Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW362 S. Jefferson Davis Pkwy (Gravier - Canal) PTP Bid & Award B Tulane - Gravier $1,036,904.00 06-Nov-13 A Spring 2014 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
PWF055 School Zone Flashing Beacons City Funded Complete ABCDE City Wide $1,793,456.00 05-Aug-08 A 29-Nov-10 A Repair and/or replacement of damaged  school zone flashers with new solar-powered flashers
DPW187 St. Anthony Path Landscape (Mirabeau - Pelopidas) City Funded Complete CD Dillard $609,660.00 14-May-12 A 22-Jan-13 A An enhancement project that may include: Extending the median along St  Anthony Ave from Mirabeau Ave to Pelopidas Ave, wideing the median to  accommodate the new walking path, additional planting of trees along the walking  path from Pelopidas Ave to Gentilly Blvd, adding a walking path along St Anthony  Ave from Gentilly Blvd to Interstate 610.
DPW188 St. Bernard Ave Streetscape Phase I (Villere - North Miro St) City Funded Pre-Construction ACD Seventh Ward $903,000.00 Early Winter  2014 Spring 2014 May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW291 St. Bernard Ave. (Filmore Ave. to Robert E. Lee Blvd.) City Funded Awaiting Bond Sale D Filmore $6,618,600.00 Summer 2015 Fall 2015 Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW189 St. Bernard Ave. (I-610 - Filmore Ave.) City Funded Complete AD St. Bernard Area $3,228,389.00 20-Nov-09 A 02-May-11 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW348 St. Bernard Ave. (N. Rampart - Sere) PTP Construction ACD Seventh Ward $3,940,205.00 01-Jun-13 A 17-Oct-13 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW184 St. Charles Ave (Calliope St - Louisiana Ave) City Funded Design B Central City $7,010,000.00 Fall 2014 Summer 2015 Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW324 St. Charles Ave (Napoleon Ave. - Louisiana Ave) City Funded Design B Milan & Touro Neighborhoods $2,900,000.00 Fall 2015 Fall 2016 Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW190 St. Charles Ave (Nashville Ave - S. Carrollton Ave) City Funded Complete A Uptown $3,035,595.00 03-Aug-09 A 06-Oct-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW281 St. Charles Ave (Nashville Ave - S. Carrollton) Bikeway City Funded Complete A Audubon $47,950.00 28-Jan-13 A 01-Feb-13 A Install  new pavement markings and signage
DPW330 St. Charles Ave (S. Carrollton - Leake) & S. Carrollton (St Charles - Leake) Roadway Rehabilitation City Funded Complete A Audubon $74,030.00 17-May-10 A 10-Jun-10 A Asphalt  pavement, base repair and curb replacement
DPW191 St. Charles Ave. (Canal St - US 90) City Funded Complete B Central Business District $958,678.00 03-Nov-09 A 10-Dec-11 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA  ramps.
DPW383 St. Charles Ave: Streetscaping Improvements Ph 1 (Callipe - S. Carrollton) City Funded Planning A City Wide $1,052,631.58 Early Winter 2015 Summer 2015 May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW375 St. Louis St. (Dauphine - Decatur) PTP Complete C French Quarter $449,782.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW370 St. Louis St. (N Rampart - Dauphine) PTP Complete C French Quarter $311,111.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW185 St. Roch and St. Claude Roadway Improvements (St. Claude Ave. - N. Roman St.) City Funded Complete C St. Roch $1,476,000.00 11-Jan-10 A 01-Nov-10 A Rehabilitation of roadway by milling existing surface and  overlay with new asphalt, including pre-milling patching repairs as well as  adjustment of utility manholes, where applicable, installation of ADA ramps  including street name tiles.
DPW326 St. Roch/St.Claude Intersection Revitalization City Funded Complete C St. Roch $210,843.00 31-Jan-13 A 18-Mar-13 A May include sidewalk or other pedestrian walkway  improvements, bikeways, traffic and pedestrian signage or signalization,  landscaping, lighting, or public art.
DPW401 Sullen Pl (Gen DeGaulle - Patterson) PTP Design C Old Aurora $2,595,700.00 Summer 2014 Early Winter 2015 Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW195 Tchoupitoulas St (Canal St - Calliope St) City Funded Complete B Central Business District $1,299,558.00 20-Mar-12 A 30-Jun-12 A Rehabilitation of roadway by milling  existing surface and overlay with new asphalt, including pre-milling patching  repairs as well as adjustment of utility manholes, where applicable.
DPW376 Toulouse St. (Dauphine - Decatur) PTP Complete C French Quarter $314,017.00 23-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW371 Toulouse St. (N Rampart - Dauphine) PTP Complete C French Quarter $315,191.00 16-Jul-12 A 31-Dec-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW196 Tulane Ave and Jeff. Davis Pkwy Streetscape - Baudin St, Clark, and D'hemecourt City Funded Complete B Mid-City $300,000.00 14-May-12 A 11-Nov-12 A May include sidewalk or other  pedestrian walkway improvements, bikeways, traffic and pedestrian signage or  signalization, landscaping, lighting, or public art.
DPW341 Tupelo St. (Douglass St. - St. Claude Ave.) PTP Complete E Lower Ninth Ward $338,763.00 09-Jul-12 A 01-Nov-12 A Remove and  replace existing roadway, install new American  with Disabilities Act-compliant curb ramps. Visit www.pavinglaroads.com for additional  detail.
DPW242 Urquhart St. (Elysian Fields Ave - Franklin Ave) City Funded Complete C St. Roch $3,649,673.00 14-Feb-11 A 11-Nov-11 A Reconstruction of existing roadway, including the replacement of affected  utilities.
DPW240 US Coast Guard Marine Debris Removal - Orleans Parish City Funded Planning E Viavant $0.00 Spring 2014 Summer 2014 Marine Debris Removal
DPW296 Veterans Admin. Medical Ctr Infrastructure Improvements (Canal, S Claiborne, Tulane, & S Rocheblave) City Funded Complete B Central Business District $13,447,530.00 06-May-10 A 11-Oct-11 A Reconstruction of existing roadway, including the replacement of  affected utilities.
DPW201 Vienna (Corinne - Nighthart) City Funded Awaiting Bond Sale E Read Blvd East $1,561,960.00 Spring 2015 Summer 2015 Reconstruction of existing roadway,  including the replacement of affected utilities.
DPW265 Washington ( S. Broad - Carrollton Ave) Bikeway City Funded Construction B Broadmoor $36,000.00 22-Aug-13 A Late Winter 2013 Install  new pavement markings and signage
DPW153 Washington Avenue Pedestrian Crossing (Washington Ave. - Drexel Drive - Xavier) City Funded Bid & Award B Broadmoor $2,995,677.00 Spring 2014 Spring 2015 Evaluation of installing a pedestrian  bridge over Washington/Palmetto Canal near Xavier University.
DPW328 West Roadway (Lake Marina Ave - South Roadway) City Funded Planning A West End $256,520.00 Early Winter 2015 Spring 2015 Asphalt pavement, base repair and curb  replacement.
DPW251 Whitney Ave & L.B. Landry (Mardi Gras Blvd - Patterson Dr) Bikeway City Funded Complete C Whitney $14,000.00 22-Aug-13 A 17-Oct-13 A Install  new pavement markings and signage
DPW211 Wisner  Bridge over I-610 City Funded Design A City Park $17,000,000.00 Fall 2014 Late Winter 2015 Bridge reconstruction
DPW256 Wisner Overlay ( Esplanade Ave - Robert E Lee) Bikeway City Funded Design A City Park $80,300.00 Early Winter 2014 Spring 2014 Install  new pavement markings and signage
DPW213 Wright Road (Chef Menteur Blvd - Dwyer Rd) City Funded Awaiting Bond Sale E Read Blvd East $8,069,430.00 Spring 2015 Summer 2015 Removal of existing roadways and replace with new hot mix asphalt  or concrete roadways including new concrete curb and gutter bottom,  rehabilitation of water and drain lines, constructing driveways, sidewalks and  handicap ramps, and all work incidental to the project as shown on the plans or  as directed by the Engineer in the field.   The width of 2 new road ways is 32 ft.  each Total project length is 2,4350 ft.   The total reconstruction shall include replacement of subsurface  utilities which includes:   3,150  ft. of new  water  lines, 4,920 ft. of new sewer lines and 5,170 ft. of new concrete drain pipes with new catch basins &  new manholes.

 

 