June 4, 2024 | From City of New Orleans
TRAFFIC ADVISORY: Poydras Street Improvements Continue with Additional Lane Closure Between Loyola Avenue and Convention Center Boulevard
NEW ORLEANS — The City of New Orleans today announced that starting at 7 a.m. on Wednesday, June 5, the Department of Public Works (DPW) contractor Hard Rock Construction, LLC will begin additional roadway improvements on Poydras Street. This includes implementing an additional lane closure between Loyola Avenue and Convention Center Boulevard to undertake street repairs. Public safety is top priority; signage and traffic control measures, such as barrels and fencing, will be onsite to direct drivers and pedestrians.
Poydras Street Improvements (Loyola Avenue – Convention Center Boulevard)
Construction crews will systematically remove and replace asphalt, focusing on one travel lane at a time. Crews will begin with the parking and outermost travel lane, moving river bound from Loyola Avenue to Convention Center Boulevard (see map). Work hours are from 7 a.m. until sunset, Monday through Friday, with some weekend work possible. All travel lanes, both river bound and lake bound, are slated to be repaved by August 2024, weather permitting.
Poydras Street Improvements (S. Claiborne Avenue – S. Liberty Street)
Simultaneously, crews will continue the process of removing and replacing concrete panels on the section of Poydras Street between S. Claiborne Avenue and S. Liberty Street (see map). Crews are currently wrapping up concrete repairs in the outer lanes and will switch the lane configurations next week to perform work in the inside lanes.
Throughout this process, two lanes will be maintained for vehicular traffic in both river bound and lake bound directions. However, due to a 30-inch water leak on the river bound side of Poydras Street at Lasalle Street, two lanes will need to be closed for safety measures. The street will remain closed until further notice as repairs are carried out in collaboration with the Sewerage and Water Board of New Orleans (SWBNO). Efforts will be made to minimize disruptions, with crews aiming to impact only one travel lane in each direction at any given time. Travelers should anticipate delays and consider alternative routes accordingly.
Work along this stretch of Poydras Steet began on May 20, 2024, and is expected to continue through the end of June 2024. The scope of work includes concrete panel repairs, pavement restoration, sidewalk and driveway apron repairs, installation of Americans with Disabilities Act (ADA) compliant curb ramps and restriping high-visibility crosswalks.
For questions about this advisory, please call 504.658.ROAD (7623) or email roadwork@nola.gov.
# # #