September 26, 2017 | From City of New Orleans

ST. CHARLES AVENUE REPAVING PROJECT REMAINS ON SCHEDULE DESPITE WEATHER-RELATED DELAYS

The $4.3M St. Charles Ave. Repaving Project, designed to remove and replace damaged portions of the asphalt roadway between Louisiana Ave. and Calliope St., is approximately 65 percent complete.

 

Despite several weather-related delays, the contractor remains on schedule and will move into the third and final phase of construction by mid-October. The third phase consist of repaving St. Charles Ave. from Felicity St. to Calliope St.

 

The scope of work includes:

  • Repaving the asphalt roadway from curb-to-curb;
  • Repairing damaged sidewalks and driveway aprons; and
  • Installing Americans with Disabilities Act-compliant curb ramps at intersections.

 

This project is a joint effort between the City of New Orleans and Louisiana Department of Transportation and Development.

 

The overall project is expected to be completed in early 2018.