October 30, 2017 | From RoadWork

MICHOUD BLVD. RECONSTRUCTION PROJECT 22 PERCENT COMPLETE

The Michoud Blvd. Reconstruction Project is approximately 22 percent complete. Last month construction crews installed several new sewer and drainage manholes at the intersection of Lourdes St. and Michoud Blvd.

RoadWork logo

October 30, 2017 | From RoadWork

YOUTH STUDY CENTER STREETS PROJECT SCHEDULED FOR COMPLETION THIS FALL

Dieudonne Enterprises, LLC construction crews are currently 75 percent complete with the Youth Study Center Streets Construction Project in the Pilotland neighborhood.

RoadWork logo

October 27, 2017 | From RoadWork

PHASE I OF FRENCH QUARTER INFRASTRUCTURE IMPROVEMENT PROJECT SCHEDULED TO BE COMPLETE IN DECEMBER

The City, its partners and construction contractors, completed construction of the 100 block of Bourbon St. in September 2017. Bollards are scheduled to be installed in November. 

RoadWork logo

October 27, 2017 | From RoadWork

S. GALVEZ ST. RECONSTRUCTION PROJECT PROGRESSING ON SCHEDULE

Command Construction Industries, LLC crews are currently 35 percent complete with the $5.4M S. Galvez St. Reconstruction Project in Central City.

RoadWork logo

October 27, 2017 | From RoadWork

WISNER BRIDGE OPEN TO VEHILCULAR TRAFFIC, CONSTRUCTION OF ADJOINING BIKE AND PEDESTRIAN APPROACHES TO BEGIN IN NOVEMBER

City and State officials celebrated re-opening of the new $19.5M Wisner Bridge in October. The bridge re-opened to vehicular traffic while a second phase of the project will connect the Wisner Bicycle and Pedestrian Path from Esplanade Avenue to the existing Wisner Path on the northern side of Interstate-610.

RoadWork logo

October 27, 2017 | From RoadWork

MAGNOLIA BRIDGE REFURBISHMENT PROJECT BID UNDER REVIEW

 The City and State are currently processing contracts to refurbish the Magnolia Bridge, which crosses Bayou St. John near Cabrini High School. Construction is tentatively scheduled to begin in early 2018.

RoadWork logo

October 27, 2017 | From RoadWork

HENRY CLAY DRAINAGE IMPROVEMENT PROJECT ON SCHEDULE TO BE COMPLETED BY HALLOWEEN

The Department of Public Works is currently working with Barriere Construction Co., LLC to improve drainage on Henry Clay Ave. between St. Charles Ave. and Hurst St.

RoadWork logo

October 27, 2017 | From RoadWork

CONSTRUCTION CREWS ON FLEUR DE LIS PHASE III PROJECT BEGIN INSTALLING DRAINAGE LINES ON NORTHBOUND LANE

Command Construction Industries, LLC crews are 25 percent complete with the Fleur de Lis Dr. Phase III Reconstruction Project between 30th St. and Old Hammond Hwy. in the West End neighborhood.

RoadWork logo

September 27, 2017 | From RoadWork

WISNER BRIDGE SCHEDULED TO REOPEN BY END OF MONTH

Construction of the new $19.5M Wisner Bridge is nearly complete and the bridge is scheduled to reopen by the end of the month. Streetlights are being energized and a pavement striping crew is schedueld to stripe the Wisner Bridge this week. The new striping will facilitate safe travel on the bridge by vehicles, bicycles and pedestrians.

RoadWork logo

September 26, 2017 | From RoadWork

CONSTRUCTION TO BEGIN IN READ BOULEVARD EAST AND WEST BEFORE THE END OF THE YEAR

Two FEMA-funded construction projects that will improve infrastructure in New Orleans East are tentatively scheduled to start construction before the end of the year. The combined value of the Read Boulevard East Group A and Read Boulevard West Group A projects is $24M.